#1
|
|||
|
|||
![]() You'll need to create a custom filter to exclude the complete tasks. The Resource in a Date Range filter can be copied and add another row with an AND condition. Include the criteria of % Complete less than 100. Repeat the process and create a new filter copied from the Resource Group filter. |
#2
|
|||
|
|||
![]()
Thank you! I'll try that.
|
#3
|
|||
|
|||
![]()
Great. Feel free to post back with any questions.
|
#4
|
|||
|
|||
![]()
I created the filter with success and the report is perfect. Thank you!
![]() |
#5
|
|||
|
|||
![]()
Great. Glad to hear all is working and thank you for the feedback.
Julie |
![]() |