JulieS JulieS is offline To Do List Report (Project 2007) Displays Completed Tasks Windows 7 64bit To Do List Report (Project 2007) Displays Completed Tasks Office 2013
Expert
 
Join Date: Dec 2011
Location: New England
Posts: 1,693
JulieS will become famous soon enough
Default

You'll need to create a custom filter to exclude the complete tasks.

The Resource in a Date Range filter can be copied and add another row with an AND condition. Include the criteria of % Complete less than 100.

Repeat the process and create a new filter copied from the Resource Group filter.
Reply With Quote
 



Similar Threads
Thread Thread Starter Forum Replies Last Post
To Do List Report (Project 2007) Displays Completed Tasks How to help - Project 2007 - Scheduling tasks during specific windows of opportunity apexian Project 1 07-12-2013 05:16 AM
To Do List Report (Project 2007) Displays Completed Tasks Creating Report based on 'Task Summary' and 'Sub Tasks' alijahed Project 1 02-01-2013 04:20 AM
To Do List Report (Project 2007) Displays Completed Tasks Change font colour when tasks are completed meileetan Project 3 09-12-2012 07:09 AM
updating not completed tasks or 0% tasks ketanco Project 3 08-24-2012 05:59 AM
Outlook completed tasks synced with Windows Mobile 6.5 ghumdinger Outlook 0 07-03-2011 07:22 AM

Other Forums: Access Forums

All times are GMT -7. The time now is 06:17 PM.


Powered by vBulletin® Version 3.8.11
Copyright ©2000 - 2025, vBulletin Solutions Inc.
Search Engine Optimisation provided by DragonByte SEO (Lite) - vBulletin Mods & Addons Copyright © 2025 DragonByte Technologies Ltd.
MSOfficeForums.com is not affiliated with Microsoft