You'll need to create a custom filter to exclude the complete tasks.
The Resource in a Date Range filter can be copied and add another row with an AND condition. Include the criteria of % Complete less than 100. Repeat the process and create a new filter copied from the Resource Group filter. |
|
![]() |
||||