![]() |
|
#1
|
|||
|
|||
|
someone showed me a ms project 2007 schedule that has activity numbers and task names are written together, in the task name column
so for example if the activity ID is 5 and tack name is painting, it says 5 Painting on task name column. how can i separate the activity IDs from Task name? They said it is written automatically |
|
|
Similar Threads
|
||||
| Thread | Thread Starter | Forum | Replies | Last Post |
any way to exclude activity from critial path
|
ketanco | Project | 1 | 10-16-2013 12:14 PM |
| tying to a critical activity | ketanco | Project | 1 | 08-04-2012 05:59 AM |
changing one activity in a baseline
|
ketanco | Project | 5 | 02-11-2012 07:24 AM |
| updating a delayed activity | ketanco | Project | 3 | 01-26-2012 01:47 PM |
change color of critical activity texts
|
ketanco | Project | 3 | 01-05-2012 06:36 PM |