Are you sure it is the Task ID - not the outline number? You can display the outline number to the left of the Task Name in the field by clicking Outline Number checkbox on the Gantt Chart Tools - Format ribbon.

Sorry, in Project 2007 you'll find the command in Tools > Options, View category.