I had the same problem and for the life of me can't understand why.

However, without really understanding, the solution is very simple - go to the gantt chart and actually shorten the bars. than - level all.
It worked for me
Reply With Quote
 



Similar Threads
Thread Thread Starter Forum Replies Last Post
Autoscheduling jumps by years in advance Converting serial number to years, months and days hannu Excel 6 02-14-2013 09:21 PM
Comparison jumps to end MarshallAbrams Word 2 03-21-2012 04:04 AM
page jumps when scrolling geoffoto Office 0 07-20-2011 07:14 PM
Picture jumps to the next page Vananil Drawing and Graphics 2 05-31-2010 01:42 AM
Autoscheduling jumps by years in advance Using Field Codes to Calculate 5 years from a Date vandy Word 1 09-23-2009 11:32 AM

Other Forums: Access Forums

All times are GMT -7. The time now is 11:59 PM.


Powered by vBulletin® Version 3.8.11
Copyright ©2000 - 2025, vBulletin Solutions Inc.
Search Engine Optimisation provided by DragonByte SEO (Lite) - vBulletin Mods & Addons Copyright © 2025 DragonByte Technologies Ltd.
MSOfficeForums.com is not affiliated with Microsoft