Autoscheduling jumps by years in advance
View Single Post
04-01-2014, 12:15 AM
Avitra
Windows 7 64bit
Office 2010 64bit
Novice
Join Date: Apr 2014
Location: Zurich
Posts: 1
I had the same problem and for the life of me can't understand why.
However, without really understanding, the solution is very simple - go to the gantt chart and actually shorten the bars. than - level all.
It worked for me
Avitra