Hi Julie

Thanks for the feedback. Unfortunately this formula does not appear to work. For example I have a task that is due to finish on 19 March and it is not being flagged at all.

Edit: Sorted - needed the True and False in quotes then it works fine.

Thanks Julie.

Tony
Reply With Quote
 

Thread Tools
Display Modes


Similar Threads
Thread Thread Starter Forum Replies Last Post
Creating a graph for Future Value function (FV function) bmoody Excel 2 11-06-2013 10:52 AM
Using DateDif Function IF function msheyworth Excel 2 03-28-2013 02:15 AM
Using DateDif Function Sum Function teza2k06 Excel 3 02-06-2013 08:29 AM
Using DateDif Function Help with DATEDIF Formula caz46 Excel 7 01-12-2012 08:46 AM
if function help jim831 Excel 2 10-29-2010 07:06 PM

Other Forums: Access Forums

All times are GMT -7. The time now is 08:04 AM.


Powered by vBulletin® Version 3.8.11
Copyright ©2000 - 2025, vBulletin Solutions Inc.
Search Engine Optimisation provided by DragonByte SEO (Lite) - vBulletin Mods & Addons Copyright © 2025 DragonByte Technologies Ltd.
MSOfficeForums.com is not affiliated with Microsoft