Hi Tony,
The Project function is DateDiff and I would use [Current Date] instead of Date().
Try:
IIf(DateDiff("d",[Finish],[Current Date])>0 And DateDiff("d",[Finish],[Current Date])<=3,True,False) in a flag field
JulieS