  #3  
Old 03-07-2014, 04:52 PM
JulieS JulieS is offline using a predecessor twice Windows 7 64bit using a predecessor twice Office 2013
Expert
 
Join Date: Dec 2011
Location: New England
Posts: 1,693
JulieS will become famous soon enough
Default

You can use milestones and a hammock task. Add a Milestone called begin taping with a SS+3day link to drywall installation. Add another milestone with a FF relationship to drywall.
Then follow the directions at the link below to create taping as a hammock.

http://support.microsoft.com/kb/141733
Reply With Quote
 



Similar Threads
Thread Thread Starter Forum Replies Last Post
using a predecessor twice Predecessor name displayed in a text field Leah Project 7 02-07-2014 03:26 PM
Linking predecessor twice ketanco Project 1 04-06-2012 08:49 AM
using a predecessor twice arrows remain between task bars, but predecessor info disappears from task info Antares Project 1 12-14-2011 09:19 AM
MS Project 2007 Predecessor Macro dmpyne Project 1 12-14-2011 08:46 AM
using a predecessor twice New to project - Predecessor Question geissap Project 1 01-20-2011 10:00 AM

Other Forums: Access Forums

All times are GMT -7. The time now is 11:58 AM.


Powered by vBulletin® Version 3.8.11
Copyright ©2000 - 2025, vBulletin Solutions Inc.
Search Engine Optimisation provided by DragonByte SEO (Lite) - vBulletin Mods & Addons Copyright © 2025 DragonByte Technologies Ltd.
MSOfficeForums.com is not affiliated with Microsoft