I don't fully understand what you are seeking. What is the place?
if you intend that two resources will work on the task for eight hours per day (16 hours in total per day) - assign two resources. Or ensure you have 200% of the resource assigned to be able to generate 16 hours of work per day. The duration is two 8 hour days the work is 32 with 16 hours of work per day for 2 days. |
![]() |
|
![]() |
||||