Hello Forum,

I need 1 resource (place) to work 20 hours a day duration and may have more hours assigned than duration. Such as, 32 hours of work but will take 16 hours to complete (2 people) leaving 4 hours remaining in day 1.

Tasks are auto scheduled. I've tried setting calendar to 20 hours working time and tasks to fixed work. I enter 32 hours in the work column and enter 16 hours in the duration column but project doesn't see to spread the hours correctly. It spreads the hours 16 hours over 2 days. Project is spreading the duration longer than the set duration.

How is the best way to set this up?

Thanks in advance