  #1  
Old 03-04-2014, 08:08 PM
Mav Mav is offline Project Hours Windows 7 32bit Project Hours Office 2010 32bit
Novice
Project Hours
 
Join Date: Mar 2014
Posts: 7
Mav is on a distinguished road
Default Project Hours

Hello Forum,

I need 1 resource (place) to work 20 hours a day duration and may have more hours assigned than duration. Such as, 32 hours of work but will take 16 hours to complete (2 people) leaving 4 hours remaining in day 1.



Tasks are auto scheduled. I've tried setting calendar to 20 hours working time and tasks to fixed work. I enter 32 hours in the work column and enter 16 hours in the duration column but project doesn't see to spread the hours correctly. It spreads the hours 16 hours over 2 days. Project is spreading the duration longer than the set duration.

How is the best way to set this up?

Thanks in advance
Reply With Quote
 



Similar Threads
Thread Thread Starter Forum Replies Last Post
Project Hours Hours in MS Project Changed ayeh Project 14 02-12-2014 10:41 AM
MS Project-timescale in hours John Franklin Project 5 10-30-2013 08:41 AM
Project Hours How to add hours together PomDave Excel 3 09-05-2011 04:43 AM
Connectivity issue of Project Professional with Project Server kashif Project 0 03-27-2009 06:37 AM
Error 9571 when opening Project Server from Project Pro mona Project 0 04-24-2007 07:50 AM

Other Forums: Access Forums

All times are GMT -7. The time now is 04:16 AM.


Powered by vBulletin® Version 3.8.11
Copyright ©2000 - 2025, vBulletin Solutions Inc.
Search Engine Optimisation provided by DragonByte SEO (Lite) - vBulletin Mods & Addons Copyright © 2025 DragonByte Technologies Ltd.
MSOfficeForums.com is not affiliated with Microsoft