Old 02-18-2014, 07:45 AM
JulieS JulieS is offline Asked to start a pmp after three months of work done Windows 7 64bit Asked to start a pmp after three months of work done Office 2013
Expert
 
Join Date: Dec 2011
Location: New England
Posts: 1,693
JulieS will become famous soon enough
Default

Project allows you to create tasks and projects with start dates in the past. Go to Project > Project Information to set the start date. Enter as much as you know. Save a baseline and then mark the tasks in the past 100% complete.
Reply With Quote
 

Thread Tools
Display Modes


Similar Threads
Thread Thread Starter Forum Replies Last Post
events show some Calendar months, not others stoddj Outlook 0 03-28-2013 07:18 AM
I'm sure this has been asked before AnthonyH Project 1 12-17-2011 07:59 AM
Asked to start a pmp after three months of work done Adding months to a Date tsindos Word 4 10-04-2011 11:20 PM
Asked to start a pmp after three months of work done chart with months windseaker Excel 1 04-29-2011 11:45 PM
Setting up recurring months to skip some months etc. dwelch@ykfireprevention.c Outlook 0 11-30-2010 10:15 AM

Other Forums: Access Forums

All times are GMT -7. The time now is 05:04 AM.


Powered by vBulletin® Version 3.8.11
Copyright ©2000 - 2025, vBulletin Solutions Inc.
Search Engine Optimisation provided by DragonByte SEO (Lite) - vBulletin Mods & Addons Copyright © 2025 DragonByte Technologies Ltd.
MSOfficeForums.com is not affiliated with Microsoft