#11
|
|||
|
|||
|
You can define the task as spanning the duration of the project. Fix the duration (Task Information) and assign the work. Project will spread the work out evenly over the long duration dropping the assignment units to a low value.
Again- leveling will not change duration nor change assignment units. |
|
|