Microsoft Office Forums

Go Back   Microsoft Office Forums > >

 
 
Thread Tools Display Modes
Prev Previous Post   Next Post Next
  #10  
Old 02-28-2014, 02:28 PM
Cycat Cycat is offline Levelling resource's units to calculate duration task Windows 7 32bit Levelling resource's units to calculate duration task Office 2010 32bit
Novice
 
Join Date: Feb 2014
Posts: 3
Cycat is on a distinguished road
Default

Thanks, I see.
Now as some method to still somehow support background tasks and Leveling I thought of some idea.
Is there a way to define some task, and give it a constraint that between Start and End day there will be at least some Minimal number of days?
This way the Leveling function will be required to split this task over a long period, even if total Work Time would allow it to complete very quickly.
Reply With Quote
 



Similar Threads
Thread Thread Starter Forum Replies Last Post
Levelling resource's units to calculate duration task Mid-Task resource scheduled 0 hours increasing task duration needlessly DarlaWeber Project 1 01-31-2014 02:30 PM
Levelling resource's units to calculate duration task Linking task duration to another task branchi Project 1 08-15-2013 06:03 AM
Levelling resource's units to calculate duration task MS Project - Maximizing resource levelling aguatorito Project 3 03-10-2013 06:08 AM
Levelling resource's units to calculate duration task How to use fixed duration, fixed work and have resources/units leveled automatically? Joeb Project 3 06-25-2012 04:18 PM
Roll-Up Duration: Changing Units of Measure & Also Accuracy Of Pmacdaddy Project 3 04-20-2012 07:13 AM

Other Forums: Access Forums

All times are GMT -7. The time now is 12:52 PM.


Powered by vBulletin® Version 3.8.11
Copyright ©2000 - 2025, vBulletin Solutions Inc.
Search Engine Optimisation provided by DragonByte SEO (Lite) - vBulletin Mods & Addons Copyright © 2025 DragonByte Technologies Ltd.
MSOfficeForums.com is not affiliated with Microsoft