Microsoft Office Forums

Go Back   Microsoft Office Forums > >

 
 
Thread Tools Display Modes
Prev Previous Post   Next Post Next
  #1  
Old 02-15-2014, 04:58 PM
codeghi codeghi is offline Levelling resource's units to calculate duration task Windows XP Levelling resource's units to calculate duration task Office 2007
Advanced Beginner
Levelling resource's units to calculate duration task
 
Join Date: Jan 2010
Posts: 38
codeghi is on a distinguished road
Default Levelling resource's units to calculate duration task

Hello from Italy, I hope for your help, I just started to use Project.


I have a problem to level the resources, I'll explain you the reason.
I have a task A with priority 1000, which has a duration of 1 year, on which the resource Giovanni is committed to 25% of his time, so I changed the units from 100% to 25% (10h a week).
Let's suppose that Giovanni do another task B with priority 500 which has a working time of 3 days (24h): if I assign the start date of the task B, how can I automatically level the units of Giovanni for task B in order to know the date of finish work of task B, and so the duration?
My desire is that Project, as a result of overallocated resource, changes the units of Giovanni on task B in order to allow Giovanni to work 6 hours a day and so complete the task B in 4 days but I'm not able!

Ciao!
Reply With Quote
 



Similar Threads
Thread Thread Starter Forum Replies Last Post
Levelling resource's units to calculate duration task Mid-Task resource scheduled 0 hours increasing task duration needlessly DarlaWeber Project 1 01-31-2014 02:30 PM
Levelling resource's units to calculate duration task Linking task duration to another task branchi Project 1 08-15-2013 06:03 AM
Levelling resource's units to calculate duration task MS Project - Maximizing resource levelling aguatorito Project 3 03-10-2013 06:08 AM
Levelling resource's units to calculate duration task How to use fixed duration, fixed work and have resources/units leveled automatically? Joeb Project 3 06-25-2012 04:18 PM
Roll-Up Duration: Changing Units of Measure & Also Accuracy Of Pmacdaddy Project 3 04-20-2012 07:13 AM

Other Forums: Access Forums

All times are GMT -7. The time now is 12:44 AM.


Powered by vBulletin® Version 3.8.11
Copyright ©2000 - 2025, vBulletin Solutions Inc.
Search Engine Optimisation provided by DragonByte SEO (Lite) - vBulletin Mods & Addons Copyright © 2025 DragonByte Technologies Ltd.
MSOfficeForums.com is not affiliated with Microsoft