#7
|
|||
|
|||
![]()
If you want Project to calculate unit requirements if you modify a task duration, set the task type as Fixed Work. In a Fixed Work task type - changing duration recalculates units and changing units recalculates duration - leaving work stable.
|
|
![]() |
||||