Microsoft Office Forums

Go Back   Microsoft Office Forums > >

 
 
Thread Tools Display Modes
Prev Previous Post   Next Post Next
  #7  
Old 02-27-2014, 06:24 AM
JulieS JulieS is offline Levelling resource's units to calculate duration task Windows 7 64bit Levelling resource's units to calculate duration task Office 2013
Expert
 
Join Date: Dec 2011
Location: New England
Posts: 1,693
JulieS will become famous soon enough
Default

If you want Project to calculate unit requirements if you modify a task duration, set the task type as Fixed Work. In a Fixed Work task type - changing duration recalculates units and changing units recalculates duration - leaving work stable.
Reply With Quote
 



Similar Threads
Thread Thread Starter Forum Replies Last Post
Levelling resource's units to calculate duration task Mid-Task resource scheduled 0 hours increasing task duration needlessly DarlaWeber Project 1 01-31-2014 02:30 PM
Levelling resource's units to calculate duration task Linking task duration to another task branchi Project 1 08-15-2013 06:03 AM
Levelling resource's units to calculate duration task MS Project - Maximizing resource levelling aguatorito Project 3 03-10-2013 06:08 AM
Levelling resource's units to calculate duration task How to use fixed duration, fixed work and have resources/units leveled automatically? Joeb Project 3 06-25-2012 04:18 PM
Roll-Up Duration: Changing Units of Measure & Also Accuracy Of Pmacdaddy Project 3 04-20-2012 07:13 AM

Other Forums: Access Forums

All times are GMT -7. The time now is 05:30 PM.


Powered by vBulletin® Version 3.8.11
Copyright ©2000 - 2025, vBulletin Solutions Inc.
Search Engine Optimisation provided by DragonByte SEO (Lite) - vBulletin Mods & Addons Copyright © 2025 DragonByte Technologies Ltd.
MSOfficeForums.com is not affiliated with Microsoft