Resource Allocation by weeks
I'm hoping there is a way to do this without creating individual tasks.
Scenario:
Thanks! |
#2
|
|||
|
|||
Given your dates it looks like there is no overlap.
But assuming the task in Project 1 was longer - the answer is no. Resource Leveling could stop Project 1 task - allow Project 2 to occur and then resume Project 1. But it cannot split a resource's time between multiple tasks. You'd need to edit the work per week in the Task Usage or Resource Usage view. |
|