ketanco ketanco is offline how to assign a labor resource more than once Windows 7 64bit how to assign a labor resource more than once Office 2007
Expert
how to assign a labor resource more than once
 
Join Date: Dec 2011
Posts: 279
ketanco is on a distinguished road
Default

ok. but if i do 200% it creates a problem when leveling later as ms project will try to level it down to 100% correct?
Reply With Quote
 



Similar Threads
Thread Thread Starter Forum Replies Last Post
how to assign a labor resource more than once Over-allocated resource - resource holiday scott.hannaford Project 1 10-21-2013 05:32 AM
how to assign a labor resource more than once Assign resource groups to tasks jjmclell Project 2 12-17-2012 04:28 AM
Which column shows just labor cost? ketanco Project 9 06-20-2012 02:19 PM
Assiging more than one labor of the same type ketanco Project 5 06-08-2012 01:28 PM
how to assign a labor resource more than once Assign functions to F1, etc. ibclare Office 4 06-02-2011 03:22 PM

Other Forums: Access Forums

All times are GMT -7. The time now is 03:35 PM.


Powered by vBulletin® Version 3.8.11
Copyright ©2000 - 2025, vBulletin Solutions Inc.
Search Engine Optimisation provided by DragonByte SEO (Lite) - vBulletin Mods & Addons Copyright © 2025 DragonByte Technologies Ltd.
MSOfficeForums.com is not affiliated with Microsoft