Microsoft Office Forums

Go Back   Microsoft Office Forums > >

 
 
Thread Tools Display Modes
Prev Previous Post   Next Post Next
  #2  
Old 02-09-2014, 07:38 AM
JulieS JulieS is offline Physical % Complete and Task Duration Windows 7 64bit Physical % Complete and Task Duration Office 2013
Expert
 
Join Date: Dec 2011
Location: New England
Posts: 1,693
JulieS will become famous soon enough
Default

Using Physical % complete is entirely manual. If based upon 20 hours of work that you are only 25% complete of the deliverable, you will need to make the adjustment your self.

Julie
Reply With Quote
 

Thread Tools
Display Modes


Similar Threads
Thread Thread Starter Forum Replies Last Post
Physical % Complete and Task Duration Mid-Task resource scheduled 0 hours increasing task duration needlessly DarlaWeber Project 1 01-31-2014 02:30 PM
Floating task duration dbsoccer Project 5 10-31-2013 09:10 AM
How to have multiple blocks of duration for one task AmezNez Project 3 10-10-2013 05:55 AM
Physical % Complete and Task Duration Linking task duration to another task branchi Project 1 08-15-2013 06:03 AM
Physical % Complete and Task Duration complete % and physical complete % ketanco Project 3 05-25-2012 08:19 AM

Other Forums: Access Forums

All times are GMT -7. The time now is 09:01 AM.


Powered by vBulletin® Version 3.8.11
Copyright ©2000 - 2025, vBulletin Solutions Inc.
Search Engine Optimisation provided by DragonByte SEO (Lite) - vBulletin Mods & Addons Copyright © 2025 DragonByte Technologies Ltd.
MSOfficeForums.com is not affiliated with Microsoft