#8
|
|||
|
|||
![]()
Do you have SP-2 installed to Project 2010? When you added the new task, did you re-baseline it? Are you looking at the baseline cost for the summary task or the detail task?
Do you have resources assigned to the summary task? |
|
![]() |
||||