![]() |
|
#8
|
|||
|
|||
|
Do you have SP-2 installed to Project 2010? When you added the new task, did you re-baseline it? Are you looking at the baseline cost for the summary task or the detail task?
Do you have resources assigned to the summary task? |
|
|
Similar Threads
|
||||
| Thread | Thread Starter | Forum | Replies | Last Post |
| MS Project-timescale in hours | John Franklin | Project | 5 | 10-30-2013 08:41 AM |
How to add hours together
|
PomDave | Excel | 3 | 09-05-2011 04:43 AM |
| Connectivity issue of Project Professional with Project Server | kashif | Project | 0 | 03-27-2009 06:37 AM |
| Error 9571 when opening Project Server from Project Pro | mona | Project | 0 | 04-24-2007 07:50 AM |
| Different % complete in Project Center & View a Project | mikaelbelchior | Project | 1 | 01-25-2006 12:56 AM |