What version of Project? If you are using Project 2010 you should be at SP-2. The baseline data is not changed by Project - is it possible that someone either manually changed the baseline or saved a new one? You mention the Baseline Cost Report - does the data appear correctly if you add the Baseline Work to a view, instead of running the report?
|