  #7  
Old 11-11-2013, 10:20 AM
JulieS JulieS is offline 12 hour work days (shifts) Windows 7 64bit 12 hour work days (shifts) Office 2010 32bit
Expert
 
Join Date: Dec 2011
Location: New England
Posts: 1,693
JulieS will become famous soon enough
Default

Are you using the 24 hours calendar as the Project calendar in Project Information? Do you have resources assigned? Are those resources assigned the base calendars of day and night shift?

If you are assigning the day and night shift calendars to the resources, and then assigning the resources to the tasks, Project will only schedule the resources during their working time. So, if I have a 36 hour duration task and assign a day shift person - the task will span longer than 36 continuous hours - the resource only works 12 hours per day - so the 36 hours spans over 3 calendar days.

If you want to be able to have a task run continuously for 36 hours then you are either going to have to assign both Day Shift and Night Shift resources or forget the day and night shift divide and just use the 24 hours calendar to schedule everything.

Ah, sorry - I saw your second post about no resources after writing all this.

So going back.

If you have the 24 hours calendar set as the Project calendar in Project Information and you want to be able to enter "3" to stand for 3 - 12 hour shifts, your definition of day needs to be 12 hours, week of 84. Duration will show as 3 days.

If you want to enter 1.5 days to stand for 36 hours (3-12 hour shifts) then set your day = 24 hours, week = 168.

Changing those values AFTER entering tasks will not recalculate the start and finish date/times - it will just show the duration in the new unit.
Reply With Quote
 



Similar Threads
Thread Thread Starter Forum Replies Last Post
12 hour work days (shifts) Calendars, 12 hr shifts, 24 hrs/ 7 days John Franklin Project 3 10-30-2013 08:16 AM
12 hour work days (shifts) 36 days task at 40% effort - only "0.86 days" in resource hanvyj Project 9 07-09-2013 07:27 AM
Can Excel Deduct 30 Minutes from an 8 1/2 Hour Cell? tatihulot Excel 4 05-16-2013 04:30 PM
Calendar work days in advance paol:o Outlook 4 05-27-2012 07:23 PM
12 hour work days (shifts) Half hour added between tasks maruchi Project 1 06-17-2010 08:06 AM

Other Forums: Access Forums

All times are GMT -7. The time now is 03:45 PM.


Powered by vBulletin® Version 3.8.11
Copyright ©2000 - 2025, vBulletin Solutions Inc.
Search Engine Optimisation provided by DragonByte SEO (Lite) - vBulletin Mods & Addons Copyright © 2025 DragonByte Technologies Ltd.
MSOfficeForums.com is not affiliated with Microsoft