I don't know what is going on. If the calendar is set to the 24Hours calendar in Project > Project Information that allows 24 hours per day in working time. If your definition of day is 12 hours, and you enter 3 days - you should see the task starting at 7:00 am and Finishing at 7:00 pm the next day. Is the date/time correct?
|