JulieS JulieS is offline Over-allocated resource - resource holiday Windows 7 64bit Over-allocated resource - resource holiday Office 2010 32bit
Expert
 
Join Date: Dec 2011
Location: New England
Posts: 1,693
JulieS will become famous soon enough
Default

The holidays should be recorded as non-working time exceptions in the Resource's calendar. Changing a resources availability by manipulation of the max units does not automatically shift the task - it just flags the resource as overallocated.



Change the resource's calendars and Project will automatically shift the task so it is worked on only during working time.
Reply With Quote
Reply



Similar Threads
Thread Thread Starter Forum Replies Last Post
resource issue safaa Project 1 11-20-2012 05:41 AM
Over-allocated resource - resource holiday Resource Allocation OTPM Project 7 10-05-2012 03:40 AM
Over-allocated resource - resource holiday Allocation of resource Tray Project 3 06-01-2012 03:09 AM
Resource Status BrownHornet Outlook 0 04-12-2012 10:47 PM
Over-allocated resource - resource holiday new name for outlook resource Rayat Outlook 1 07-05-2011 04:12 AM

Other Forums: Access Forums

All times are GMT -7. The time now is 03:04 PM.


Powered by vBulletin® Version 3.8.11
Copyright ©2000 - 2026, vBulletin Solutions Inc.
Search Engine Optimisation provided by DragonByte SEO (Lite) - vBulletin Mods & Addons Copyright © 2026 DragonByte Technologies Ltd.
MSOfficeForums.com is not affiliated with Microsoft