  #2  
Old 10-04-2013, 05:27 AM
JulieS JulieS is offline Auto Adjust After Early Finish Windows 7 64bit Auto Adjust After Early Finish Office 2010 32bit
Expert
 
Join Date: Dec 2011
Location: New England
Posts: 1,693
JulieS will become famous soon enough
Default

There is no automatic way for Project to know that the task only took 3 days instead of 5 without you telling it. Display the Tracking table, set the Actual Finish to the finish date, the task will be marked 100% complete, the actual duration will show 3 days. Assuming the successor task is linked and does not have an actual start date, it will adjust accordingly.
Reply With Quote
 



Similar Threads
Thread Thread Starter Forum Replies Last Post
providing early start date ketanco Project 1 02-22-2013 02:32 PM
Keep with Next/Keep Lines Together (to adjust page breaks) lewiskm55 Word 1 05-02-2011 08:18 AM
Pasting HTML into Excel (height auto-adjust) c-tran Excel 0 03-11-2010 07:30 AM
how do i adjust column to chosen width hill0093 Word 0 09-19-2009 05:24 AM
Adjust speed of ppt animation gerryb PowerPoint 0 08-15-2009 08:45 AM

Other Forums: Access Forums

All times are GMT -7. The time now is 12:54 AM.


Powered by vBulletin® Version 3.8.11
Copyright ©2000 - 2025, vBulletin Solutions Inc.
Search Engine Optimisation provided by DragonByte SEO (Lite) - vBulletin Mods & Addons Copyright © 2025 DragonByte Technologies Ltd.
MSOfficeForums.com is not affiliated with Microsoft