hanvyj hanvyj is offline 36 days task at 40% effort - only "0.86 days" in resource Windows XP 36 days task at 40% effort - only "0.86 days" in resource Office 2010 32bit
Advanced Beginner
36 days task at 40% effort - only "0.86 days" in resource
 
Join Date: Feb 2012
Posts: 33
hanvyj is on a distinguished road
Default

I've checked working time calendar, the only non-working time is the weekends. I'm not sure what you mean by resource leveled? I certainly haven't tried to do it :S
Reply With Quote
 

Thread Tools
Display Modes


Similar Threads
Thread Thread Starter Forum Replies Last Post
36 days task at 40% effort - only "0.86 days" in resource How do I get auto-updated "number of days since specified date" on MS word? terry795 Word 16 01-07-2016 04:33 PM
36 days task at 40% effort - only "0.86 days" in resource 5 days/week during planning & 7 days/week during implementation sanlen Project 1 06-25-2012 04:17 PM
Resources "Available From" Date in resource sheet bluphoto Project 3 04-05-2012 09:33 AM
How to have the "days" in other languages? Jamal NUMAN Excel 6 08-26-2011 08:34 AM
36 days task at 40% effort - only "0.86 days" in resource How to choose a "List" for certain "Heading" from "Modify" tool? Jamal NUMAN Word 2 07-03-2011 03:11 AM

Other Forums: Access Forums

All times are GMT -7. The time now is 11:00 PM.


Powered by vBulletin® Version 3.8.11
Copyright ©2000 - 2025, vBulletin Solutions Inc.
Search Engine Optimisation provided by DragonByte SEO (Lite) - vBulletin Mods & Addons Copyright © 2025 DragonByte Technologies Ltd.
MSOfficeForums.com is not affiliated with Microsoft