JulieS JulieS is offline 36 days task at 40% effort - only "0.86 days" in resource Windows 7 64bit 36 days task at 40% effort - only "0.86 days" in resource Office 2010 32bit
Expert
 
Join Date: Dec 2011
Location: New England
Posts: 1,693
JulieS will become famous soon enough
Default

Is this a file that you can zip and email to me? I'll take a look.
Reply With Quote
  #2  
Old 07-09-2013, 07:23 AM
hanvyj hanvyj is offline 36 days task at 40% effort - only "0.86 days" in resource Windows XP 36 days task at 40% effort - only "0.86 days" in resource Office 2010 32bit
Advanced Beginner
36 days task at 40% effort - only "0.86 days" in resource
 
Join Date: Feb 2012
Posts: 33
hanvyj is on a distinguished road
Default

Quote:
Originally Posted by JulieS View Post
Is this a file that you can zip and email to me? I'll take a look.
Sorry, I wasn't being clear. It's fixed! I'm not sure how it happened, but somehow the assignments managed to get different end dates to the task so the "Task View" looked like this: (hope whitespace works properly)

-Task1 35 days Thu 11/04/13 Thu 30/05/13
- Bob Bobson 0 days Thu 11/04/13 Thu 11/04/13

So Bob Bobson was down for that task, but his assignment was 40% of 0 days. Changing the assignments end dates to match the task end dates fixed the issue.

The only thing is how it got like that in the first place, I'd never been in the Task view before.
Reply With Quote
Reply



Similar Threads
Thread Thread Starter Forum Replies Last Post
36 days task at 40% effort - only "0.86 days" in resource How do I get auto-updated "number of days since specified date" on MS word? terry795 Word 16 01-07-2016 04:33 PM
36 days task at 40% effort - only "0.86 days" in resource 5 days/week during planning & 7 days/week during implementation sanlen Project 1 06-25-2012 04:17 PM
Resources "Available From" Date in resource sheet bluphoto Project 3 04-05-2012 09:33 AM
How to have the "days" in other languages? Jamal NUMAN Excel 6 08-26-2011 08:34 AM
36 days task at 40% effort - only "0.86 days" in resource How to choose a "List" for certain "Heading" from "Modify" tool? Jamal NUMAN Word 2 07-03-2011 03:11 AM

Other Forums: Access Forums

All times are GMT -7. The time now is 05:36 AM.


Powered by vBulletin® Version 3.8.11
Copyright ©2000 - 2025, vBulletin Solutions Inc.
Search Engine Optimisation provided by DragonByte SEO (Lite) - vBulletin Mods & Addons Copyright © 2025 DragonByte Technologies Ltd.
MSOfficeForums.com is not affiliated with Microsoft