JulieS JulieS is offline 36 days task at 40% effort - only "0.86 days" in resource Windows 7 64bit 36 days task at 40% effort - only "0.86 days" in resource Office 2010 32bit
Expert
 
Join Date: Dec 2011
Location: New England
Posts: 1,693
JulieS will become famous soon enough
Default

Does Bob Bobson have non-working time in his calendar? Have you resource leveled Bob?
Reply With Quote
 

Thread Tools
Display Modes


Similar Threads
Thread Thread Starter Forum Replies Last Post
36 days task at 40% effort - only "0.86 days" in resource How do I get auto-updated "number of days since specified date" on MS word? terry795 Word 16 01-07-2016 04:33 PM
36 days task at 40% effort - only "0.86 days" in resource 5 days/week during planning & 7 days/week during implementation sanlen Project 1 06-25-2012 04:17 PM
Resources "Available From" Date in resource sheet bluphoto Project 3 04-05-2012 09:33 AM
How to have the "days" in other languages? Jamal NUMAN Excel 6 08-26-2011 08:34 AM
36 days task at 40% effort - only "0.86 days" in resource How to choose a "List" for certain "Heading" from "Modify" tool? Jamal NUMAN Word 2 07-03-2011 03:11 AM

Other Forums: Access Forums

All times are GMT -7. The time now is 12:09 AM.


Powered by vBulletin® Version 3.8.11
Copyright ©2000 - 2025, vBulletin Solutions Inc.
Search Engine Optimisation provided by DragonByte SEO (Lite) - vBulletin Mods & Addons Copyright © 2025 DragonByte Technologies Ltd.
MSOfficeForums.com is not affiliated with Microsoft