#1
|
|||
|
|||
|
Because it is the only task with zero total slack. Critical path is calculated by project. Without further information - I can't give a more complete answer, sorry.
|
|
#2
|
|||
|
|||
|
Quote:
Please find attached here a sample project file. Project A has duration of 3 days, B has 2 days and C has 1 day. Please review the network diagram. Task A is on Critical path. If you change the duration of the tasks B & C as 3 days each, then they will also become "critical". Even if you change the start date of Task A to June 05, 2013 (keeping the same duration), it will show Task A as "critical". Will you please explain why this happnes? Thanks |
|
| Thread Tools | |
| Display Modes | |
|
|
Similar Threads
|
||||
| Thread | Thread Starter | Forum | Replies | Last Post |
How to show critical task bars in different color?
|
ketanco | Project | 1 | 05-17-2012 05:17 AM |
Microsoft Project 2010 SYNC Problem
|
paul14louie | Project | 3 | 04-13-2012 11:36 AM |
| Microsoft Project 2010 automation without VS | Fil | Project | 0 | 09-15-2011 10:17 AM |
| MS Project 2010 Synch to task list | rinalgi1 | Project | 1 | 09-14-2011 12:37 AM |
Microsoft Project 2010 taking up to 10mins to open file from network share.
|
BITS | Project | 1 | 06-01-2011 09:37 AM |