Hi,
So, you are working 4 days per week, 10 hours per day from 5:30 pm to 4:00 am. I'm going to guess you start Monday at 5:30 pm and end on Friday at 4:00 am. For the purposes of the steps below, I am assuming you work from 5:30 pm until 12:30 am - break for 1/2 hour and re-start at 1:00 am and work until 4:00 am. If your break times are different - adjust as needed.
In Project 2010:
Project tab
- Change working time button to open the Change Working Time dialog box.
- Click the Work Weeks tab
- Click the Details button to open the Details for [Default] dialog.
- Click on Monday and click the button "Set these days to specific working times".
- Enter 5:30 pm in the From
- Enter 12:00 am in the To column
- Click on the number 2 to the left of the second row and hit the delete key on your keyboard to delete the second row of times.
- Click on Tuesday and Shift Click on Thursday to highlight Tuesday, Wednesday, and Thursday.
- Click the button "Set these day to specific working times"
- Enter 12:00 am in the From column
- Enter 12:30 am in the To
- Second Row
- Enter 1:00 am to 4:00 am
- Third Row
- Enter 5:30 pm to 12:00 am
- Click in the fourth row but do not enter anything
- Select Friday on the left and click the button "Set these days to specific working times"
- Enter 12:00 am in the From column
- Enter 12:30 am in the To column
- Second Row
- Enter 1:00 am to 4:00 am
- Click in the Third row but do not enter anything.
- Click the OK button to close the Details for [Default] dialog and return to the Change Working Time dialog.
- Click the Options button.
- Set the Default start to 5:30 pm
- Default end to 4:00 am
- Hours per day to 10
- Hours per week to 40.
- Click OK to close the Project Options dialog.
- Click OK to close the Change Working Time dialog.
I hope this helps. Post back with any further questions.
Julie