![]() |
#1
|
|||
|
|||
![]() I have project plan and i have one month in the miidel of the project out of project schedual but MS Project include that month in day caculation so how to correct that |
#2
|
|||
|
|||
![]()
If no work is going to occur during the month - make the month non-working by changing the Project calendar. Assuming you are using Project 2010 - Project tab, Change Working Time icon.
Julie |
![]() |
Tags |
project days |
Thread Tools | |
Display Modes | |
|
![]() |
||||
Thread | Thread Starter | Forum | Replies | Last Post |
![]() |
sanlen | Project | 1 | 06-25-2012 04:17 PM |
![]() |
Mosey | Outlook | 2 | 10-31-2011 06:47 AM |
convert 3months and 15 days into 3.5 | caz46 | Excel | 5 | 09-05-2011 03:29 AM |
Connectivity issue of Project Professional with Project Server | kashif | Project | 0 | 03-27-2009 06:37 AM |
Error 9571 when opening Project Server from Project Pro | mona | Project | 0 | 04-24-2007 07:50 AM |