Thread: Project Days
View Single Post
 
Old 12-17-2012, 04:27 AM
JulieS JulieS is offline Windows 7 64bit Office 2010 32bit
Expert
 
Join Date: Dec 2011
Location: New England
Posts: 1,693
JulieS will become famous soon enough
Default

If no work is going to occur during the month - make the month non-working by changing the Project calendar. Assuming you are using Project 2010 - Project tab, Change Working Time icon.

Julie
Reply With Quote