If no work is going to occur during the month - make the month non-working by changing the Project calendar. Assuming you are using Project 2010 - Project tab, Change Working Time icon.

Julie
Reply With Quote
Reply

Tags
project days



Similar Threads
Thread Thread Starter Forum Replies Last Post
Project Days 5 days/week during planning & 7 days/week during implementation sanlen Project 1 06-25-2012 04:17 PM
Project Days How to reorder the days of the week Mosey Outlook 2 10-31-2011 06:47 AM
convert 3months and 15 days into 3.5 caz46 Excel 5 09-05-2011 03:29 AM
Connectivity issue of Project Professional with Project Server kashif Project 0 03-27-2009 06:37 AM
Error 9571 when opening Project Server from Project Pro mona Project 0 04-24-2007 07:50 AM

Other Forums: Access Forums

All times are GMT -7. The time now is 06:27 AM.


Powered by vBulletin® Version 3.8.11
Copyright ©2000 - 2025, vBulletin Solutions Inc.
Search Engine Optimisation provided by DragonByte SEO (Lite) - vBulletin Mods & Addons Copyright © 2025 DragonByte Technologies Ltd.
MSOfficeForums.com is not affiliated with Microsoft