Microsoft Office Forums

Go Back   Microsoft Office Forums > >

 
 
Thread Tools Display Modes
Prev Previous Post   Next Post Next
  #2  
Old 11-08-2012, 05:50 AM
JulieS JulieS is offline Elapsed Time, mandays &% complete Windows 7 64bit Elapsed Time, mandays &% complete Office 2010 32bit
Expert
 
Join Date: Dec 2011
Location: New England
Posts: 1,693
JulieS will become famous soon enough
Default

Hi Liz,

I'm afraid the scenario isn't going to work. % Complete is a duration measurement - so if you change the finish date (increase duration) Project will automatically drop the % complete. Even with manually scheduled tasks, changing the finish date to a later date will drop the % complete.

You may be able to come closer using % Work complete and fixed work tasks. If you set your tasks as fixed work - and you adjust duration - project simply recalculates assignment units.

Julie
Reply With Quote
 



Similar Threads
Thread Thread Starter Forum Replies Last Post
Elapsed Time, mandays &% complete complete % and physical complete % ketanco Project 3 05-25-2012 08:19 AM
IE Object: Run-time problem (the link is not clicked in run-time but not in step-in tinfanide Excel Programming 1 03-04-2012 12:05 AM
Elapsed Time, mandays &% complete % Complete (Actual) vs % Complete (Should) Carlos Maximo Project 3 12-06-2011 12:01 PM
Reporting ManDays on people not fully assigned to the Project Imagios Project 9 10-10-2011 04:36 AM
Elapsed Time, mandays &% complete Calculate elapsed time in Word table? Snvlsfoal Word Tables 1 08-11-2011 05:42 AM

Other Forums: Access Forums

All times are GMT -7. The time now is 09:30 PM.


Powered by vBulletin® Version 3.8.11
Copyright ©2000 - 2025, vBulletin Solutions Inc.
Search Engine Optimisation provided by DragonByte SEO (Lite) - vBulletin Mods & Addons Copyright © 2025 DragonByte Technologies Ltd.
MSOfficeForums.com is not affiliated with Microsoft