View Single Post
 
Old 11-08-2012, 05:50 AM
JulieS JulieS is offline Windows 7 64bit Office 2010 32bit
Expert
 
Join Date: Dec 2011
Location: New England
Posts: 1,693
JulieS will become famous soon enough
Default

Hi Liz,

I'm afraid the scenario isn't going to work. % Complete is a duration measurement - so if you change the finish date (increase duration) Project will automatically drop the % complete. Even with manually scheduled tasks, changing the finish date to a later date will drop the % complete.

You may be able to come closer using % Work complete and fixed work tasks. If you set your tasks as fixed work - and you adjust duration - project simply recalculates assignment units.

Julie
Reply With Quote