#2
|
|||
|
|||
![]()
I'm afraid you can't have it both ways -- if you want the remaining work from in progress tasks to be moved - you need to allow tasks to be split. If you want to have completed work remain and the finish date updated - you'll need to manually increase duration one by one.
|
|
![]() |
||||