JulieS JulieS is offline correcting split tasks Windows 7 64bit correcting split tasks Office 2010 32bit
Expert
 
Join Date: Dec 2011
Location: New England
Posts: 1,693
JulieS will become famous soon enough
Default

Tasks get split if you don't have any work entered on a day. If the tasks is 100% complete, it has an actual start and actual finish. Rejoining the task may drop the % complete below 100%.

I don't know why you are concerned about the split - it merely reflects reality. The task was started, stopped, restarted.
Reply With Quote
 



Similar Threads
Thread Thread Starter Forum Replies Last Post
Priority based levelling for split tasks having actuals proj12 Project 3 02-27-2012 06:47 AM
Export Excel tasks into Outlook Tasks (2007 Version on both) crazedmom Excel 0 12-29-2011 07:55 AM
Split a task fridos Project 2 05-30-2011 11:19 AM
correcting split tasks voice control: correcting mispelled words persist Word 1 05-11-2011 04:58 AM
correcting split tasks How to stop correcting zeroes in cells ? kevin_ms Excel 4 09-14-2008 10:08 PM

Other Forums: Access Forums

All times are GMT -7. The time now is 02:51 PM.


Powered by vBulletin® Version 3.8.11
Copyright ©2000 - 2025, vBulletin Solutions Inc.
Search Engine Optimisation provided by DragonByte SEO (Lite) - vBulletin Mods & Addons Copyright © 2025 DragonByte Technologies Ltd.
MSOfficeForums.com is not affiliated with Microsoft