Thread: [Solved] correcting split tasks
View Single Post
 
Old 08-15-2012, 08:05 AM
ketanco ketanco is offline Windows 7 64bit Office 2007
Expert
 
Join Date: Dec 2011
Posts: 279
ketanco is on a distinguished road
Default correcting split tasks

when i was updating one of my schedules, some of the tasks got splitted although i didnt want (which are now complete). there are quite a few of them.

1-how can i make those past 100% tasks show as continuous bars? is there a shortcut to do all of them at once? or should i go to them one by one?

2-whatever the answer is for question 1, what is the best method to do that?