![]() |
|
#4
|
|||
|
|||
|
Earned value is calculated, by default, against the Baseline. You can change which baseline earned value is calculated from through Tools > Options, Calculation tab - earned value button. However, you cannot use different baselines for different tasks.
I hope this helps. |
| Thread Tools | |
| Display Modes | |
|
|
Similar Threads
|
||||
| Thread | Thread Starter | Forum | Replies | Last Post |
| Calculating Profits? | MarkL | Project | 1 | 06-12-2012 07:19 AM |
calculating duration
|
ketanco | Project | 5 | 12-15-2011 07:15 PM |
Calculating dates
|
Daria11 | Word VBA | 1 | 06-08-2011 06:54 PM |
How to apply budget for earned value analysis
|
ttorneby | Project | 2 | 06-03-2010 04:52 PM |
| Good commission to be earned for writing some office questions | iqnetsys | Office | 0 | 02-23-2009 05:22 AM |