Hi
Im using Project 2010 and want to know if I can have two sets of Start / Finish dates showing as separate bars on the Gantt chart? I have the columns inserted in the tasks section using the default Start / Finish and also entered two additional columns using the Start 1 & Finish 1 headings. These latter two do not show on the Gantt - can it be done? thanks |
#2
|
|||
|
|||
![]()
You'll need to create the bar in the bar styles dialog. (Format tab) Cut and paste twice the existing bar -- change the draw from and to to the correct fields. I'd drop it to row 2 unless you want to change the width of the existing bars.
I hope this helps. Julie |
![]() |
|
![]() |
||||
Thread | Thread Starter | Forum | Replies | Last Post |
![]() |
ketanco | Project | 1 | 05-17-2012 05:17 AM |
![]() |
Antares | Project | 1 | 12-14-2011 09:19 AM |
![]() |
criddell | Outlook | 4 | 09-18-2011 03:40 PM |
gantt bars with text and i'm losing the bar when i print | oompa_l | Project | 0 | 11-17-2010 01:16 PM |
how to make the task starts next day if no time enough today(task can not be split) | duraid | Project | 1 | 10-25-2010 08:31 AM |