  #1  
Old 07-23-2012, 06:05 AM
JulieS JulieS is offline Change Resource Time vs. Duration when Updating Work column Windows 7 64bit Change Resource Time vs. Duration when Updating Work column Office 2010 32bit
Expert
 
Join Date: Dec 2011
Location: New England
Posts: 1,693
JulieS will become famous soon enough
Default

Set you task types as fixed duration and then as you change work, duration will remain stable and the peak units will change.



You may add the "Type" field to the task view to change many tasks easily OR select all tasks (except summary), click the Information button on the Task tab, and set the task type on the Advanced tab.

I hope this helps.

Julie
Reply With Quote
Reply

Tags
duration, resource, work



Similar Threads
Thread Thread Starter Forum Replies Last Post
updating status date and actual duration ketanco Project 5 01-27-2012 07:32 AM
Can I change the horizontal scrollbar to scroll smoothly rather than column by column carpat Excel 0 01-10-2012 09:34 AM
Change Resource Time vs. Duration when Updating Work column baseline duration of summary not updating. why ketanco Project 1 12-14-2011 09:07 AM
Work not changing duration benoldays Project 0 02-14-2011 08:21 PM
Duration changes fail to update work effort Panteledes Project 6 05-25-2010 02:27 PM

Other Forums: Access Forums

All times are GMT -7. The time now is 08:25 PM.


Powered by vBulletin® Version 3.8.11
Copyright ©2000 - 2025, vBulletin Solutions Inc.
Search Engine Optimisation provided by DragonByte SEO (Lite) - vBulletin Mods & Addons Copyright © 2025 DragonByte Technologies Ltd.
MSOfficeForums.com is not affiliated with Microsoft