![]() |
|
#1
|
|||
|
|||
|
Hi,
We have working days for our project as below: 1. during the planning stage, we are only working from Monday to Friday. 2. after the planning (implementation), our sub-contractor will be working 7 days a weeks (Monday - Sunday). I have broken down the activities into different milestones and put in one Ms Project 2010 file. However, i cannot figure out how to tell Ms Project that all planning milestones will be with 5 working days a week and all implementation milestones will be working 7 days a week. Can you please advise how to get this done? |
|
#2
|
|||
|
|||
|
The tasks being performed by the contractor will use the contractor's calendar if you create the assignment.
Have you created the 7-day per week base calendar? Did you assign that calendar as the base for the resources? Julie |
|
| Thread Tools | |
| Display Modes | |
|
|
Similar Threads
|
||||
| Thread | Thread Starter | Forum | Replies | Last Post |
Conditional Formatting per Week
|
mrgy05 | Excel | 2 | 06-07-2012 10:38 AM |
How to reorder the days of the week
|
Mosey | Outlook | 2 | 10-31-2011 06:47 AM |
Work Week: hours vary each day
|
rkc | Outlook | 1 | 08-31-2011 01:17 PM |
Calander work week
|
cfawcett22 | Outlook | 1 | 08-06-2011 01:46 PM |
| Change Calendar to 4 day work week | J C M | Outlook | 1 | 04-28-2011 02:20 PM |