5 days/week during planning & 7 days/week during implementation
Hi,
We have working days for our project as below:
1. during the planning stage, we are only working from Monday to Friday.
2. after the planning (implementation), our sub-contractor will be working 7 days a weeks (Monday - Sunday).
I have broken down the activities into different milestones and put in one Ms Project 2010 file. However, i cannot figure out how to tell Ms Project that all planning milestones will be with 5 working days a week and all implementation milestones will be working 7 days a week.
Can you please advise how to get this done?
|