#1
|
|||
|
|||
![]()
Hi
I want to set up a task that lasts 7 days, and can be started up to 60 days after it's predecessor. Can this be done without setting an actual date (relative). I'm currently trying not to hard-set any date, because I want the whole project to be movable, by using indentation. |
|
![]() |
||||