An option for your statement"
Quote:
Task 9 lasts 3 days, and I have up to 60 days, starting from the end of task 4 to complete it.
|
is to create a Finish to start relationship with a 60 day lag between task 9 and task 4. This will allow Task 9 to adjust 60 days relative to the completion of Task 4. I would still set a deadline on Task 9 just so you are alerted if it starts to slip.
You are very welcome for the assistance.
Project is quite different than any other Office product and has a bit of a learning curve. There are some pretty good how to videos (free) from the folks at Microsoft. See:
http://www.microsoft.com/project/en-us/2010-videos.aspx
to get you started.
Feel free to drop by with more questions as needed. Good luck.
Julie