Hello,
I entered the labor resources into resource sheet including their rates. And when I assign resources the cost column shows the total cost, but that is the total cost column, not just labor. If I had a fixed cost, the cost column would reflect the total of fixed cost plus the cost calculated from assiginng the labor resource. I could not find the column that would show me the cost for labor only. Which column is that? |
|
![]() |
||||