View Single Post
 
Old 06-20-2012, 02:19 PM
JulieS JulieS is offline Windows 7 64bit Office 2010 32bit
Expert
 
Join Date: Dec 2011
Location: New England
Posts: 1,693
JulieS will become famous soon enough
Default

Quote:
now for the material, i went into my resource sheet and saw that there is a material type there. when i did that i can only enter value to standard rate. a single lump sum value for that material. so this means, material may only be a lump sum entry correct?
No. You can define material resources per unit. For example gallons of paint. You then define the cost per gallon.

You may then assign 5 gallons of paint to a task, and Project will calculate units * rate to show cost for that material resource for that task.

Quote:
for the cost resource type however when i changed the type to cost, all fields just closed for entry. i can not enter any value anywhere. Or do i need to insert a certain column?
You enter the cost for the cost resource when you assign it. Click on a task, click the assign resources button and you'll see a cost field in the assign resources dialog.
Reply With Quote