Material costs comes from assigning resources defined as Material resources in the Resource Sheet View.
Cost resources are also a type of resource defined on the Resource Sheet view.
Project calculates the Cost field. The other cost fields (Cost1 through Cost10) are custom fields that you may use to perform calculations of store other cost information outside of the calculated Cost field.
|