#1
|
|||
|
|||
![]()
When I am assigning labor to my activity, for, say, concrete pouring, I have 5 labors that have exactly the same cost. So do I use 5 separate concrete labor assignments to that activity? So in the resource sheet I go as Concrete Labor CL1, CL2, CL3, CL4, CL5 and so on and assign them separately? Or I just have one CL resource in the resource sheet and assign that CL to the activity but in that case how do I show 5 labors will be working on it?
|